{카테고리_이름} Drazice OKC 400 NTRR/HP/SOL에 대한 운영 및 설치 매뉴얼을 온라인으로 검색하거나 PDF를 다운로드하세요. Drazice OKC 400 NTRR/HP/SOL 13 페이지. Indirect water tanks
2.4 CONNECTION OF TANK TO HOT WATER DISTRIBUTION SYSTEM
The tank is placed on the ground, next to the heating source, or in its vicinity. The heating circuit shall be
connected to marked tank exchanger inputs and outputs, and bleeder valve installed at the highest point.
It is necessary to install a filter into the circuit in order to protect pumps, three-way valve, backflow flaps
and the exchanger from sedimentation. It is recommended to flush the heating circuit before the assembly.
All wiring connections must be properly insulated from heat. If the system works with priority heating
of HUW using a three-way valve, always follow the installation instructions of the three-way valve's
manufacturer.
An example of a group tank connection for steady hot water consumption from all tanks using
Tichelmann's method
HW - Heating water
CV - Cold water
C - Circulation
Figure 5
HWS - Hot service water
1 - Return valve
2 - Pump