Boiler room arrangements

The Multi-elec Standard must be installed:
In an adequately-ventilated boiler room with ambient temperature below 30°C
and relative humidity maintained between 30% and 80% and where condensation
does not occur
In a non-corrosive atmosphere
In a non-explosive atmosphere
Where there is good access to the boiler position for installation and maintenance
Where there is good access for delivery, off-loading and positioning
Using similar materials in the in the pipework, and avoiding materials leading to electrolytic
action and system deterioration
The Multi-elec Compacte is not suitable for external installation
2.6

Commissioning

The boiler must be completely full of water before the heating elements are switched on.
To ensure 100% filling, manual and automatic vents must be in effective positions where
complete air clearance can be guaranteed.
The boiler can be filled with water by connecting a fill hose to the boiler drain valve and partly
opening the valve.
The boiler safety valve can also be used firstly to vent the boiler at filling and, secondly,
ensuring the blow-down facility of the valve is clear in case of use.
Commissioning is recommended by Atlantic 2000 or an authorised engineer for
Atlantic equipment.