1. EXCAVATION
Anchor Slab
Above U-Leg
T = per Structural Engineer
3. SUPPORT LUMBER ATTACH
Locate and Drive Grade
Stakes Where Needed
Align and Set Channels to Grade.
Secure to Grade Stakes.
5. CHANNEL PLACE & ALIGN
T
T
Tie Wire
Caulk Channel Joints as Specified
Finished Grade
Elevation
T
1/2" Min
Above Dirt
Grade Stake
Caulk or Adhesive
(as Specified)
4. DISCHARGE PLACE & ALIGN
Locate and Align Outlet Channel First. Start
at Deep End and Work to Shallow End.
Install Remaining Leg
Bracket Screws After
Positioning Channels
6. RAIL CONNECTION
2. LEG ATTACH
Set Top of Rails to
Finished Elevation
Blank or Horiz. Outlet
End Plate (as Specified)
Vertical Outlet Piping
(as Specified)
End Rail