{카테고리_이름} cashco 6987에 대한 설치 운영 및 유지보수을 온라인으로 검색하거나 PDF를 다운로드하세요. cashco 6987 9 페이지. Back pressure / relief regulator
10. Basic Regulator- (See Figure 1): Regulator
may be rotated around the pipe axis 360°.
Rec om mend ed po si tions are with spring cham ber
ver ti cal upwards, or hori zon tal. Orient such that
the spring chamber vent hole does not collect
rain wa ter or debris.
11. Regulators are not to be direct buried un der ground.
12. For insulated piping systems, rec om men da tion is
to not in su late reg u la tor.
III. PRINCIPLE OF OPERATION
1. Movement occurs as pressure variations reg is ter
on the diaphragm. The registering pressure is
the inlet, P
or upstream pressure. The range
1
spring opposes dia phragm move ment. As
inlet pressure drops, the range spring pushes
IV. STARTUP
1. Start with the block valves closed. A bypass valve
may be used to maintain inlet pressure in the
up stream system without chang ing the following
steps.
2. Relax the range spring by turning the adjusting
screw counterclockwise (CCW) a minimum of
three (3) full revo lu tions. This reduces the inlet
(upstream) pres sure setpoint.
3. If it is a "hot" piping system, and equipped with
a bypass valve, slowly open the bypass valve
to pre-heat the system piping and to allow slow
ex pan sion of the piping. Closely mon i tor inlet
(up stream) pres sure, via gauge, to assure not
over-pres sur iz ing. NOTE: If no bypass valve is
in stalled, extra caution should be used in starting
up a cold system; i.e. do ev ery thing slowly.
4. Crack open the inlet (upstream) block valve.
5. Slowly open the outlet (downstream) block
valve ob serv ing the inlet (upstream) pressure
gauge. De ter mine if the regulator is flowing. If
not, slowly rotate the regulator adjusting screw
counter clock wise (CCW) until flow be gins.
6. Continue to slowly open the outlet (down stream)
block valve until fully open.
2
The maximum inlet pressure is equal to 1.5 times the larger
number of the stated range spring on the name plate, and is
the recommended "upper operative limit" for the sens ing
di a phragm. Higher pressures could damage the di a phragm.
(Field hy dro stat ic tests fre quent ly destroy di a phragms.
DO NOT HY DRO STAT IC TEST THROUGH AN IN STALLED
UNIT; ISOLATE FROM TEST.)
SECTION III
the dia phragm down, closing the port; as inlet
pressure in creases, the dia phragm pushes up
and the port opens.
2. A complete diaphragm failure may cause the
valve to fail closed.
SECTION IV
7. Observing the inlet (upstream) pressure gauge,
ro tate the ad just ing screw clockwise (CW) slowly
until the inlet pressure begins to rise. Rotate CW
until the desired setpoint is reached.
8. Continue to slowly open the inlet (upstream) block
valve. If the inlet (upstream) pressure ex ceeds
the desired set point pressure, rotate the adjusting
screw CCW until the pressure decreases.
9. When flow is established steady enough that both
the outlet and inlet block valves are fully open,
begin to slowly close the bypass valve if installed.
10. Develop system flow to a level near its expected
normal rate, and reset the regu la tor set point by
turning the ad just ing screw CW to increase inlet
pressure, or CCW to reduce inlet pressure.
11. Reduce system flow to a minimum level and
observe set point. Inlet pressure will rise from the
setpoint of Step 9. (Ensure that this rise does not
exceed the stated upper limit of the range spring
by greater than 50%, i.e. 50 - 100 psig (3.4 - 6.9
Barg) range spring, at maximum flow the inlet
pressure should not ex ceed 1.5 x 100 psig (6.9
Barg), or 150 psig (10.3 Barg). If it does, consult
factory.)
12. Increase flow to maximum level if possible. Inlet
(up stream or P
setpoint as necessary at the normal flow rate.
WARNING
) pressure should fall off. Readjust
1
IOM-6987