CPI 400
Installation Manual
Closed position indicator that visually and electrically displays when the valve is either in the closed or open position. Mounts
directly to the DMV, SV, MVD and HSAV series valves. When the valve is closed (NO position) a orange light is visible, when
the valve is open (NC position) a green light is visible.
Gases
Natural gas, Propane, Noncorrosive gases, and Air
Switch Type
SPDT
Switch Action
valve open:
switch in NC position, Green light
valve closed: switch in NO ,position, Orange light
Contact Rating
10 A res, 8 FLA, 48 LRA @120 Vac
Enclosure
NEMA 4 when 1/2" NPT to PG11 adapter is sealed
with RTV.
• Read these instructions carefully.
• Failure to follow them and/or improper installation may
cause explosion, property damage and injuries.
• Installation must be done with the supervision of a
licensed burner technician.
• The system must meet all applicable national and local
code requirements.
• Check the ratings above and on the switch
to make sure that it is suitable for your application.
Mounting
• The valve must be de-energized and the gas supply shut
off before mounting the CPI 400.
• Disconnect all power to the switch before beginning to
prevent electrical shock and equipment damage.
Mounting Procedure (reference Fig. 1 on page 2)
• IMPORTANT!! Before mounting the bass adapter to the
valve or to the CPI 400, use your fingers to verify that
the pin slides freely inside the brass adapter. If this
pin is does not slide freely, apply a large enough force
to the appropriate side to free the pin.
• Using a 5 mm hex wrench, remove the plug and its oring
located at the bottom of the valve.
• Verify that the brass adaptor has a clean oring, and its
threads and the groove, into which the brass adapter
mounts, are clean and in good condition.
• Mount the brass adapter into the valve.
• Use a 9/16" (14 mm) open end wrench and turn 1/4
to 1/2 additional turn (after finger tight). DO NOT over
•524 Apollo Drive Suite 10 Lino Lakes, MN 55014, U.S.A. • Phone 651-792-8912 • Fax 651-792-8919
SPECIFICATIONS
INSTALLATION
• Never perform work if gas pressure or power is applied,
or in the presence of an open flame.
• Protect surfaces. Make sure that seals and O - rings are
clean and in good condition.
• Once installed, perform a complete checkout including
a gas leak test.
• Label all wires prior to disconnecting when servicing
switches. Wiring errors can cause improper and danger-
ous operation.
• Verify proper operation after servicing.
tighten.
• Mount the CPI switch onto the brass adaptor. Push the
CPI housing towards the valve until it stops.
• Turn/Position the CPI so that the wiring and condiut con-
nection apply the least amount of torque as possible.
• Tighten the set screw so that the CPI housing is secured
to the brass adaptor.
• Do not turn the CPI 400 after tightening the set screw; this
may strip the brass adatper. The brass adaptor could
loosen and the asembly may leak.
• Perform a leak test to verify that no leakage occurs around
the oring.