Casio QT-6600 설치 및 다운 복구 매뉴얼 - 페이지 14
{카테고리_이름} Casio QT-6600에 대한 설치 및 다운 복구 매뉴얼을 온라인으로 검색하거나 PDF를 다운로드하세요. Casio QT-6600 16 페이지. Touch screen smart terminal
Casio QT-6600에 대해서도 마찬가지입니다: 사양 (4 페이지), 설치 및 다운 복구 매뉴얼 (3 페이지)
![Casio QT-6600 설치 및 다운 복구 매뉴얼](/uploads/products/server2/1695129/1695129.jpg)
- 1. From Cf Card to a Terminal
- 2. 1-1.How to Load Ipl (Initial Program Loading
- 3. Stand Alone System (with External Printer / Slip Printer
- 4. 1-2.How to Install the System
- 5. System down and Recovery
- 6. Check Tracking Master Terminal Failure
- 7. 2-3.Recovery Processing
- 8. Master/Backup Master down Detection
Down Recovery
2-3.
Recovery processing
2-3-1.
Master/backup master down detection
←Cut off Master/BM icon
ß
←System error icon
¶
2-3-2.
When both master and backup master go down
2-4.
Master failure during X/Z collection/consolidation or terminal data transfer
2-5.
Satellite terminal down
I-14
With the QT-6600 system, the processing being performed can be continued by a backup
master even when a master goes down. However, at the end of the daily operations, the
master which has been down should be restored so that it can operate normally on the next
day.
1) After daily operations, check the "Cut off Master/BM" icon.
2) If the icon is lit on any terminal, the system has been downed in the day.
3) Turn off / on the master and backup master (not by the <Disp on/off> key but by the main
power switch in the power switch cover).
4) After this operation, the "System error" icon is lit on the master (or backup master) or
both master/backup master.
5) In case of the icon of one terminal is lit, disconnect this terminal from the inline and
repair it. If the icon of both terminal are lit, both master have been downed. This case,
jump to the next section.
6) Issue open check reset report on the alive master or backup master terminal.
7) Connect the restored master terminal with the inline, initialize it and download the
terminal program from the other master.
8) Perform the "System Re-configuration" at the restored master terminal.
1) Restore both masters immediately, load the program file to them.
2) Perform the "System Re-configuration" at the master terminal.
With the master goes down during X/Z collection / consolidation or transfer of terminal
program file, it is necessary to take the following procedure:
1) When the master goes down during Z collection / consolidation, the satellite is not
released from locked condition.
2) In this case, press the <ESC> key twice at that satellite to release the locked condition.
3) After step 2), cut off the downed master from the system connection table and perform
Z collection / consolidation from other terminal.
This command should be issued by the good (not downed) terminal.
When the satellite terminal goes down during check tracking registration, the check
number cannot be used for other terminal.
In this case, performing the "Busy Reset" command in the manager mode releases this flag.