DURAVIT 7509 사전 설치 - 페이지 9

{카테고리_이름} DURAVIT 7509에 대한 사전 설치을 온라인으로 검색하거나 PDF를 다운로드하세요. DURAVIT 7509 10 페이지.

DURAVIT 7509 사전 설치

Pre-installation Checklist

REQUIREMENTS
I. INSTALLATION ROOM / ROOM CONDITIONS
Temperature range 15 - 40 °C
Load bearing capacity given and checked in advance
Installation position, doors, stairs etc. suitable for transport of
individual parts (space and weigh), manoeuvring space checked
Ceiling height min. 2350 mm
Room width and height requirements for minimum clearances
guaranteed
Floor and wall completely level or straight, at right angles to each
other
Air inlet, exhaust and room dehumidification assured
II. CHARGING STATION ELECTRICAL CONNECTION
Electrical socket for charging station available
III. SAUNA ELECTRICAL CONNECTION
Test electricity supply earth
(planned, according to electrician)
Circuit breaker Installed
(planned, according to electrician)
IV. WATER CONNECTION (ONLY INIPI AMA)
Water connection available in designated zone
Water drain available in designated zone
V. RADIO CONNECTION (RECOMMENDATION)
Radio connection (FM) in designated zone
Radio connection (AM) in designated zone
REMEDY
Modify floor/wall
Install ventilation Equipement
(ventilation connection potential)
Install electrical socket
Lay Electrical Connection
Install circuit breaker
Install water feed
Install water drain
Lay coaxial cable (FM)
Lay coaxial cable (AM)
SAUNA_VID_Inipi_Inipi-Ama/15.07.7
9