TRT03
If the name plate voltages are not entered, TRT03 will perform the test and display the results, but it will not
calculate or display the turns ratio deviation. After the name plate voltages and tap changer position(s) are
entered, press
to confirm a selection. The next display allows a selection of the test voltage.
ENTER
Figure 3-2:
The test voltage
selection
TRT03 generates single-phase test voltage. TRT03 supplies a single-phase excitation test voltage to each
of the three transformer primary windings in turn. The induced voltages across each of the corresponding
unloaded transformer windings are then measured. The ratio of these voltages is calculated and presented
on the display. It is repeated for all three phases.
Test voltage of 8 V and 10 V is recommended for current transformers (CT) testing. For testing distribution
or power transformers it is recommended to use the highest test voltage of 100 V or 80 V. Otherwise a test
voltage of 40 V can also be used. Pressing
confirms it by pressing
ENTER
TRT03 automatically detects if it is connected to a DC power supply. It also automatically detects if the
power supply frequency is 50 Hz or 60 Hz. The frequency of the output voltage is the same as the frequency
of the power supply of TRT03. In case TRT03 is connected to a DC power supply, the user has to choose
the frequency of the output voltage to be either 50 Hz or 60 Hz.
After the test voltage (and frequency) is selected, the user can select a memory location manually (Test
Reading and Test Record).
Selection of Test Reading or Test Record is performed by using
selection.
Test Reading can contain, for example, all the test results obtained in one tap changer position of the
transformer. Test Record can contain the results of all tap changer positions, or the complete results
obtained from one transformer.
Note: Manual selection of record/reading will delete results from the existing memory locations.
Once these parameters are defined, pressing
Figure 3-3:
The READY state
before the test
If one of the values has to be changed, press
The flashing green LED indicates TRT03 is now ready to start the test. Press
the test, the red LED glows continuously signaling that the test voltage is applied. Pressing
CONFIGURATION menu is displayed) will interrupt (abort) the test. When the test is completed, TRT03
displays the test results. To scroll between all the results press
can choose whether to test the next tap or to finish the test.
M-T003NN-205-EN
UP/DOWN
.
is used to scroll between the Test Reading and Test Record options.
SET
ENTER
to return to the previous menu.
STOP
10
the user selects the value of his/her choice and then
UP/DOWN
changes the status to the READY state.
. Once all the results are viewed, user
ENTER
Getting Started
. Pressing
confirms a
ENTER
to run a test. During
START
STOP
(the