CORNING SCF-1728 매뉴얼 - 페이지 6
{카테고리_이름} CORNING SCF-1728에 대한 매뉴얼을 온라인으로 검색하거나 PDF를 다운로드하세요. CORNING SCF-1728 14 페이지. Heat shrink open ribbon system (hs-ors) canister splice closure
Step 6: If more than one cable is being installed in the oval port, position the 3-finger clip between the two
cables at the end of the heat-shrink tube (Figure 11).
Step 7:
Hold the cable while heating to prevent any movement.
Step 8: Beginning at the port, gradually move a heat gun down the tube. Allow this portion of the tube to
cool before shrinking the rest of the tube onto the cable.
9.
Attach Frame to End Cap
Step 1:
Remove splice plane and slack storage covers
TPA-6367
Step 2:
Secure the end cap on the work surface (table) with the express cable to the top.
Step 3:
Lay all the ribbon fiber from the express ports in a bundle in the middle storage area (Figure 13).
Step 4: Hold the express fibers in one hand and the ORS frame in the other hand.
Step 5:
Carefully reposition the ORS frame and secure it to the end cap.
IMPORTANT:
Make sure the end cap is oriented so that the express cables transition smoothly into the middle
storage area of the frame with no sharp bends in the cable.
3-finger Clip
Section
Figure 12.
Standard Recommended Procedure 206-455-AEN | Issue 1 | November 2018 | Page 6 of 14
TPA-3746
Figure 11
Figure 12