CORNING EDGE8-04U 설치 및 테스트 - 페이지 5

{카테고리_이름} CORNING EDGE8-04U에 대한 설치 및 테스트을 온라인으로 검색하거나 PDF를 다운로드하세요. CORNING EDGE8-04U 13 페이지. Tap module
CORNING EDGE8-04U에 대해서도 마찬가지입니다: 설치 및 테스트 (8 페이지)

CORNING EDGE8-04U 설치 및 테스트
Step 6:
Clean and install an LC to LC
jumper- Reference Jumper
no. 2 (RJ2) into M1 and the LC
adapter (Figure 7).
Step 7:
Verify that the RJ1/ RJ2 mated pair are acceptable with a loss ≤0.10 dB for
multimode and ≤0.20 dB for single-mode.
Step 8:
Disconnect RJ2's LC connector from the LC adapter and protect it with a clean dust
cap until you are ready to start the system testing.
Step 9:
Clean and install an LC to LC
jumper-Reference Jumper
no.3 (RJ3) into M2 and the LC
adapter (Figure 8).
Step 10: Verify that the RJ1/RJ3 mated pair are acceptable with a loss ≤0.10 dB for
multimode and ≤0.20 dB for single-mode.
Step 11:
Disconnect RJ1's LC connector from the LC adapter and protect it with a clean dust
cap.
Step 12: Leave the LC adapter on the end of RJ3 for the remainder of this procedure since it
will be required for mating to the TAP port test harness.
7.3
Referencing is now complete.
IMPORTANT: From this step on, do NOT disconnect the connectors on either the Light Source or
meter port adapters.
STANDARD RECOMMENDED PROCEDURE 003-139-AEN | ISSUE 1 | JANUARy 2017 | PAGE 5 OF 13
multimode only
RJ1
Do NOT
disconnect
Light
Source
HPA-0759
Dust cap
multimode only
RJ 1
Do NOT
disconnect
Light Source
HPA-0760
LC
adapter
Reference
Jumper no. 2
RJ2
Do NOT
disconnect
Do NOT
disconnect
LC
adapter
RJ3
0.3 dB
0.15 dB
M2
0.15 dB
M1
Figure 7
RJ2
M1
Figure 8