alkitronic HSD 200 운영 및 유지보수 매뉴얼 - 페이지 10

{카테고리_이름} alkitronic HSD 200에 대한 운영 및 유지보수 매뉴얼을 온라인으로 검색하거나 PDF를 다운로드하세요. alkitronic HSD 200 16 페이지. Mounting documentation system

Operation and Maintenance Manual
1850
Nm
8 R
O
OK
The system will start with a pause of five seconds. If more
bolting processes are due, the counter will increment and the
total number of completed bolting processes and the grand
total are displayed on the screen.
If the <Enter> key is pressed during the pause the system will
be ready for the next bolting process immediately.
Once the predefined number of bolting process has been
reached the program will terminate and the main menu
appears on the display.
End?
>
No
Yes
Make the selection with the > cursor
with the <Enter> key.
5.3.4 Assessment criteria
Depending on the assessment described below the result is
stored in memory:
Status
> (minus 1°) or equal target angle
< or > target angle
> max. torque
< min. torque
< max. torque and > min. torque
5.3.5 Documentation data
Value
Content
Year/Month/Day/hours/minutes
ID
Global counter ID (incremented by each process)
Program
3
Current torque
Maximum during measurement
Target angle
As defined
Current angle
Maximum during measurement
Min. torque
As defined
Max. torque
As defined
Status
OK/ Not OK
Screen display: The currently
measured max. torque, the max
rotation angle with direction.
Note:
If during a screwing process the
<Enter> key is pressed, there will
be a confirmation query prompt
on the screen: End program?
and confirm
( ↓ ) ( ↑ )
Result
OK
Not OK
Not OK
Not OK
OK
5.4
Bolting program 4
Exclusively for the
HSD model of
MDS product range.
Make the program
selection in the
main menu.
5.4.1 Application description
This program determines the required rotation angle, for
example for the use in testing and development projects.
Pre-torque and target and final torque are predefined. Mea-
surement and storage of achieved rotation angle.
5.4.2 Parameter setting
Number of rotation
angle determinations
Target torque
Pre-torque
When setting the parameters always check for
plausibility: The pre-torque must be smaller than
the target torque. All torque predefinitions must
be between the minimum and maximum torque
values of the torque multiplier (see parameter table
4.1).
5.4.3 Process description
During the tightening process the torque increases conti-
nuously. When the torque reaches the switching threshold
(value see parameter table 4.1) the program will continue to
display the latest max. torque and the rotation angle.
If the measured torque exceeds the predefined pre-torque
the rotation angle measurement will be started.
If the measured torque exceeds the target torque the rotation
angle measurement is terminated. If the measured torque
drops below the switching threshold the process is saved to
memory.
2050
Nm
18
R
O
2 / 10
10
The parameters on the left-
must all be entered to ensure
correct data recording and
evaluation.
Screen display: the current
measured max. torque, the
number of completed screwing
processes, as well as the grand
total.