6.1.4 Cabinet Power Cable Connection:
1. Install the power distribution cabinet and install it near the screen according to the
site conditions to avoid the main power cable being too long.
2. Install the cabinet, refer to Chapter 6.
3. After the cabinet is installed, connect the power cord according to the design
drawings.
Figure 6-1 shows the connection of the power cable of the VRR P10 display.
①power distribution cabinet
②main power cord
③power cascade
6.2 Signal Cable Connection
6.2.1 Sender Box
The sending box contains a sending card to send video data to the display.
6.2.2 Main Signal Cable
Send the main signal line between the box and the display screen to transmit video
data with a length of less than 70m.
Remarks: When the transmission distance is greater than 70m, it is possible to
transmit data by optical fiber, and the longest distance is 20 kilometers.
Signal cascading line: used for signal transmission between cabinets.
6.2.3 Cabinet Signal Cable Connection:
1. During the installation process, pay attention to the protection of the cabinet to
Install the send box, arrange the main signal, and put it next to the display installation
position.
2. Install the cabinet, refer to Chapter 6.
3. After the cabinet is installed, connect the signal wires according to the design
drawings.
Figure 6-2 shows the connection of signal lines in the arrangement of VRR P10 1*46.
Each main network cable carries 128*96*46=565,248 pixels. In the figure:
① indicates the sending box
13 / 50