9 - INSTALLATION PROCEDURE
Minimum operation and maintenance area.
A
Find the space for the installation of the return
B
air grille and mark the opening to do. Cut the
falseceiling.
Mark on the ceiling the holes for the hanging rods,
D
verify the distance of the centres.
900 (ADIAS19)
(ADIB-CS13)
Use rawl plug suitable to the ceiling consistence
C
and four M10 threaded bars of suitable lenght (not
supplied).
Drill a 65/80 mm diameter hole, for the passage of
E
refrigeration pipework, condensate pipework and
electrical cable. Insert a PVC pipe in the wall.
7
EN