Installing the Server in a Rack

Supported Cisco Slide Rail Kits
The server supports the following rail kit options:
• Cisco part UCSC-RAILB-M6= (ball-bearing slide rail kit)
• Cisco part UCSC-RAILF-M6= (friction slide rail kit)
• Cisco part UCSC-CMAF-M6= (cable management arm)
Rack Installation Tools Required
The slide rails sold by Cisco Systems for this server do not require tools for installation.
Slide Rail and Cable Management Arm Dimensions
The slide rails for this server have an adjustment range of 24 to 36 inches (610 to 914 mm).
The optional cable management arm (CMA) adds additional length requirements:
• The additional distance from the rear of the server to the rear of the CMA is 5.4 inches (137.4 mm).
• The total length of the server including the CMA is 35.2 inches (894 mm).
Installing the Server in a Rack
Warning
Step 1
Attach the inner rails to the sides of the server:
a) Align an inner rail with one side of the server so that the three keyed slots in the rail align with the three pegs on the
side of the server.
b) Set the keyed slots over the pegs, and then slide the rail toward the front to lock it in place on the pegs. The front slot
has a metal clip that locks over the front peg.
c) Install the second inner rail to the opposite side of the server.
Cisco APIC M4/L4 Server Installation and Service Guide
22
To prevent bodily injury when mounting or servicing this unit in a rack, you must take special
precautions to ensure that the system remains stable. The following guidelines are provided to
ensure your safety:
This unit should be mounted at the bottom of the rack if it is the only unit in the rack.
When mounting this unit in a partially filled rack, load the rack from the bottom to the top with
the heaviest component at the bottom of the rack.
If the rack is provided with stabilizing devices, install the stabilizers before mounting or servicing
the unit in the rack.
Statement 1006
Installing the Server