Internal service platform (full area)
(only for S15E xxxx-11xE and S15E xxxx-12xE units
The Internal Service Platform (full area) and access ladder is factory installed, no field installation is required.
The platform can be accessed by opening the sliding grid.
Push upwards on one side of the grid to
open
Internal ladder only
Depending on model the internal ladder is supplied in two parts. Only in this case, slide the two half ladders
into the pre-installed U-channels.
Install bolts M10
Note: The ladder can also be oriented towards the fill pack (similar procedure).
8
W W W . B A L T I M O R E A I R C O I L . E U
Slide the grid sideways.
Always close the sliding grid when standing on the platform.
Make sure the grid is secured by sliding it
to the end position (lock in place).
Caution
Lift the ladder into place and drop the pre-welded bolts
into the mounting holes in the upper support channel.
No further fastening is required.
)