Great Lakes UL60950-1 Installation Instructions Manual - Page 5

Browse online or download pdf Installation Instructions Manual for Racks & Stands Great Lakes UL60950-1. Great Lakes UL60950-1 8 pages. 4 post equipment racks
Also for Great Lakes UL60950-1: Installation Instructions Manual (13 pages), Installation Instructions Manual (12 pages)

Great Lakes UL60950-1 Installation Instructions Manual

FLOOR INSTALLATION

Once the location on the floor has been determined, inspect the floor surface. The floor must be flat
and square in the horizontal and vertical plane to ensure the 2 Post Rack is installed correctly.
WARNING: Improper handling and use of the 2 Post Rack could result in equipment damage,
serious injury, or possible death.
MASONRY FLOOR SURFACE
For a masonry floor surface, the installer must provide all the appropriate hardware.
POWER
When using PDUs, each PDU should be connected to a committed branch circuit that is rated for the
continuous load of all the equipment connected. When not using a PDU, each piece of equipment
should be connected to a dedicated branch circuit.

PROTECTIVE EARTHING/GROUNDING

A main protective earthing lug is provided.
WARNING: To avoid injury to persons or loss of life, ground each 2 Post Rack individually to the
dedicated branch circuit earthing ground.
CONNECT MAIN PROTECTIVE EARTHING STUD TO THE DEDICATED BRANCH CIRCUIT EARTHING
GROUND CONDUCTOR
Locate and attach the main protective earthing lug to the 2 Post Rack and secure set screws.
Connect the dedicated branch circuit earthing ground conductor to the main protective lug.
5