Dea SWINGER Operating Instructions And Warnings - Page 7

Browse online or download pdf Operating Instructions And Warnings for Gate Opener Dea SWINGER. Dea SWINGER 13 pages. Electro-mechanical operator for swing gates
Also for Dea SWINGER: Operating Instructions Manual (20 pages)

Dea SWINGER Operating Instructions And Warnings

6 START-UP

The start-up phase is very important to ensure maximum security and compliance to regulations, including all the requirements of EN
12445 standard which establishes the test methods for testing the automation for gates.
DEA System reminds that all installation, maintenance, cleaning or repair operations on any part of the system must be performed
exclusively by qualified personnel who must be responsible of all texts requie by the eventual risk;

6.1 Installation test

The testing operation is essential in order to verify the correct installation of the system. DEA System wants to summarize the proper
testing of all the automation in 4 easy steps:
• Make sure that you comply strictly as described in paragraph 2 "WARNINGS SUMMARY";
• Test the opening and closing making sure that the movement of the leaf match as expected.
We suggest in this regard to perform various tests to assess the smoothness of the gate and defects in assembly or adjustment;
• Ensure that all safety devices connected work properly;
• Perform the measurement of impact forces in accordance with the standard 12445 to find the setting that ensures compliance with
the limits set by the standard EN12453.
WARNING Using spare parts not indicated by DEA System and/or incorrect re-assembly can create a risk to people, animals and
property and also damage the product. For this reason, always use only the parts indicated by DEA System and scrupulously follow all
assembly instructions.

6.2 Unlocking and Manual operation

In the event of malfunctions or simple power failure, release the motor (Pic. 9) and perform the operation manually.
The knowledge of the unlocking device is very important because, in times of emergency, lack of speed in operating this device can
cause danger.
WARNING The efficancy and safety of manual operation of the automation is guaranteed by DEA System only if the installation has
been installed correctly and with original accessories.

7 MAINTENANCE

Good preventive maintenance and regular inspection ensure
long working life. In the table below you will find a listo f inspections/
maintenance operations to be programmed and executed periodi-
cally.
Consult the TROUBLE-SHOOTING" table whenever anomalies are
observed in order to find the solution to the problem and contact
DEA System directly whenever the solution required is not provided.
Description
When the opening command is given, the gate wing fails to
move and the operator's electric motor fails to start.
When the opening command is given, the motor starts but
the gate leaf fails to move.
The operator jerks or is noisy during movement, it stops
midway or else it does not start.
EN-6
INTERVENTION TYPE
cleaning of external surfaces
checking of screw tightening
checking of release mechanism operation
greasing of articulated joint
TROUBLE-SHOOTING
The operator is not receiving correct power supply. Check all connections, fuses, and the
power supply cable conditions and replace or repair it if necessary. If the gate does not close
check if the photocells work properly.
Make sure the unlocking system is closed.
Make sure that the electronic device for power adjustment is in good condition.
If the leaf of the gate does not move freely, release the operator and readjust the rotation
points.
The power of the gearmotor may be insufficient for the characteristics of the gate's leaf;
check the choice of model whenever required.
If the plate fastening the operator to the gate bends or is inappropriately fastened, repair it
or reinforce it.
Possible solutions
PERIODICITY
6 months
6 months
6 months
1 year