Fill the first syringe again, open the bleeder valve and fill in further
brake-fluid. Look at the reservoir while filling to see if air bubbles are
coming out of the line. Fill up to 15 mm (0.6 in.) below the upper edge
of the reservoir.
-
Close the bleeder valve, reinstall the membrane and the cap to the
reservoir and remove the bleeder assy.
-
Check brake pressure according to step 3..
-
Reinstall the main wheel.
3. Check brake pressure:
-
Extend the airbrakes, there must be a strong pressure when the wheel
brake engages.
-
Check several times, the wheel brake must engage at the same point
every time
-
If this is not the case, you have to bleed the system again, see step 5..
4. Check the hydraulic brake system for leaks:
Extend the airbrakes with high force and hold it in this position for 2
minutes.
Then check the whole hydraulic system visually for leaks. If necessary
tighten the screwed joints or replace the sealings and bleed the system
again.
Note: The adjustment of the length of the cable between the master cylinder and
the airbrake control shaft restricts the max. airbrake extension height. The
adjustment of this cable should be done with the glider rigged.
5. Bleeding the hydraulic brake system
Remove the brake fluid from the reservoir using the syringe.
Then execute again steps 2 and 3 of this instruction.
6. Exchanging brake fluid (every 4 years)
-
Perform preparations (see step 1.) of this instruction. It is not
necessary to remove the main wheel.
-
Fill the system with new brake fluid (see step 2.). To accomplish this
remove all brake fluid from the reservoir first with the second syringe.
Used brake fluid is darker than new brake fluid and can easily be
identified. Watch the reservoir while filling to see when the new fluid
streams into the reservoir. Repeat the filling process until only new
fluid is in the system and no air bubbles can be detected.
-
Perform steps 3. and 4. of this instruction.