Disconnect the machine from the power supply and ensure that power cannot be switched on again in error.
Remove the machine lid.
Remove the cover from the electrical panel on the back of the machine.
bl
br
gn
blue
brown
green
Table 1: Wire Colors
Warning!
Load and control wiring harnesses should be separated from one another in order to avoid noise in the control wiring
(electromagnetic compatibility).
Warning!
Lay any extra wiring in the opposite direction in order to avoid antenna-like behavior in the wires.
Secure relay K1/81 (Fig. 1, Pos. 1) via the heater channel to the existing hole on the brace using one 4x10 screw.
Disconnect the existing connection to ELP 430-A
Feed wiring harness 55X-X3 (Fig. 1, Pos. 2) to terminal block X3 (Fig. 1, Pos. 4) via the conduit in the machine
chassis.
Connect wiring harness 55X-X3 to relay K1/81 and to ELP 430-A
Connect wiring harness 55X-X3 to terminal block X3 (Fig. 1, Pos. 4). Observe the wiring diagram, wire colors and the
5 imprinted on the brown wire; see Fig. 1, Pos. 4.
Secure wiring harness 55X-X3 to the wiring harness near the main terminal block using the 200x4.8 cable tie.
Knock out the pre-cut hole for the external peak load cut-out module in the connection strip on the back of the
machine.
Secure the M20x1.5 screw for the external peak load cut-out module to the connection strip on the back of the
machine.
Connect the external peak load cut-out module (Fig. 1, Pos. 5) to terminal block X3 (Fig. 1, Pos. 4) following the
module manufacturer's instructions.
Warning!
If no external peak load cut-out module is connected to terminal block X3, use the brown wire to jumper pins 4 and 5.
Perform a test run.
Re-install the cover on the electrical panel on the back of the machine.
Re-install the machine lid.
Carry out appropriate electrical safety checks.
Reconnect the machine to the electrical supply.
Note
Check the release point for peak load in all programs.
am
16.06.2010
Diese Unterlagen dürfen ohne unsere Genehmigung weder vervielfältigt noch Dritten zugänglich gemacht werden. Eigentumsrechte vorbehalten.
ge
gr
or
yellow
gray
orange
55X (Fig. 1, Pos. 3).
Umbau- und Montageanweisung
rs
rt
sw
pink
red
black
55X.
M.-Nr. 07724490
vi
ws
violet
white