Prior to installing the bay assembly, you should prepare your slab or raised floor plan.
Slab Floor Plan
Level Equipment
Temporarily position and level using metal shims and the equipment frame.
Drill Slab Floor
Step 1
Mark the slab floor for the anchoring holes using either the provided template or by positioning the rack
in the desired location.
page 8
rack aside.
Drill the anchoring holes into the slab using a masonry drill bit. Make sure the masonry dust is removed
Step 2
from the holes.
Reposition the rack over the holes. Depending on the type of slab floor mounting hardware used, the
Step 3
anchors may need to be inserted into the holes before the rack is repositioned.
Relevel the rack using metal shims if necessary.
Step 4
Install the bay assembly according to local site practice.
Step 5
78-15720-04
Figure 4 on page 8
shows fiber routing for a slab base. After the floor marks have been made, move the template or
Unpacking and Installing the Cisco ONS 15454 Four-Shelf and Zero-Shelf Bay Assembly
shows a rack cross section with cabling routes.
Installation Instructions
Figure 5 on
7