ABB ACH580-31 Quick Installation And Start-Up Manual - Page 7
Browse online or download pdf Quick Installation And Start-Up Manual for Control Unit ABB ACH580-31. ABB ACH580-31 16 pages. Converter modules with electrolytic dc capacitors in the dc link
Also for ABB ACH580-31: Manual (16 pages)
10. Connect the control cables
Make the connections according to the application. Keep the signal wire pairs twisted as near to the terminals as possible
to prevent inductive coupling.
1.
Cut a hole into the rubber grommet and slide the grommet onto the cable with the remaining cone pointing down.
2.
Ground the outer shield of the cable 360 degrees under the grounding clamp. Keep the cable unstripped as close to the
terminals of the control unit as possible. Ground also the pair-cable shields and grounding wire at the SCR1 terminal.
3.
Tie all control cables to the provided cable tie mounts.
Default I/O connections (Water default)
Total load capacity of the auxiliary voltage output +24V (X2:10) is 6.0 W (250 mA / 24 V DC).
Terminals
+24V, DGND, DCOM, B+, A-, DGND, Ext. 24V
DI, AI, AO, AGND, RO, OUT, IN, SGND
R6... R only: Ext 24V AC/DC input to power up the
control unit when the main supply is disconnected.
Wire size
2
0.14 ... 2.5 mm
(26 ... 14 AWG)
2
0.14 ... 2.5 mm
(26 ... 14 AWG)
Tightening torque
0.5 ... 0.6 N·m (0.4 lbf·ft)
7