STEP 6: PURLINS
Items:
3x
ST-PT35701630 (Purlin)
12x 70mm SCREW
Principle of purlins
installation
Side purlins
Middle purlin
STEP 7: ROOF BOARDS
Items:
2x
MFP - 1800x970x10
36x 35mm SCREW
Principle of floor boards installation
Use 35mm screws. Keep equal distance between screws. Make
sure that each screw is fixed into timber underneath the board.
Front view to inside
(Front panel have been removed for illustration
purposes only.)
35mm SCREW
MFP board
Assembly Steps
Pre-drill parts before fixing with screws
6a) Position the middle purlin as shown in the diagram and secure it by using 4x 70mm
screws (2x 70mm screws on each end of purlin).
6b) Position the remaining purlins in between the center purlin and the side walls. Use 2x
70mm screws per each purlin and secure them on the top and bottom. See image below
(1.0).
Flush
70mm SCREW
SIDE
7a) Position MFP onto the roof and ensure the overhang is equal for the front and rear.
7b) Secure the MFP to the purlins by using equally spaced 35mm screws. Use 18
screws per MFP board.
MFP board
Side view - Middle purlin connection
(1.0)
(Some components have been removed
for illustration purposes only.)
Middle purlin
Window
Pre-drill parts before fixing with screws
35mm SCREW
FRONT
70mm SCREW