STEP 3: START Up
Before proceeding with start-up, verify the
following items have been completed:
- All installation has been completed and verified.
- All wiring has been completed and verified.
- Power is present at the AVC6 and verified to spec.
- Exhaust system is operating with static pressure control.
- The configuration PC has Insight loaded and operational.
3a. Connect PC to FHM3
3b. On the AIRFLOW SETPOINT Gauge, Select MODE
3c. Verify the Mode of Operation is set to FUME HOOD MODE
The Calibration Tools provided for Fume Hood Mode are
accessed through a series of buttons that are positioned in the
order of which they should be completed during the initial start
up.
www.accutrolllc.com or www.AccuValve.com
Plug USB "C" Cable from PC into
the FHM3 USB Port at the bottom
of the Monitor.
Open the AVC Insight
UI Program.
3d.
Select Configure Fume Hood Type and enter the
information required.
3e. Select Calibrate Sash
Input if sash sensors are employed and perform the sash
calibration procedure.
3f. Select Configure Control Setpoints and enter the setpoint
information required for the application.
3g. Select Configure Purge Mode and select the appropriate
Purge configuration per the application requirements.
3h. Select Configure Alarms and enter the alarm setpoint
information required for the application.
4.
After completing the above steps, verify the displayed face
velocity correlates with the measured average face velocity.
Be sure the average face velocity field measurement is
obtained using appropriate methods and instrumentation
per industry standards and facility requirements.
5.
If desired, the displayed face
velocity can be correlated to
the field measured face
velocity by using the Face
Velocity Measurement
Adjust function, which can
be accessed through the
utilities Menu under Tools.
This document is a quick-start reference only and is not
intended to be used exclusively as a comprehensive
guide for the AVC6 Fume Hood Control System. For more
details, refer to the AVC6 User Manual, submittal
drawings and job specifications to obtain the required
operating parameters.
2