CTEK CGC100 Installatiehandleiding

4 Functionality

The load monitor and charging stations can be
used immediately after installation and
commissioning/configuration.
CHARGESTORM® Connected shows the
electric vehicle charging status using symbols.
See user manual, ref. 2).
4.1
Vehicle charging
Connect the charging cable to the vehicle. The
green outlet symbol will change to a flashing
blue battery and charging will begin.
To stop charging, disconnect the cable from
the car.
4.2
Maintenance
The residual current device should be tested
once a year.
4.3
Resetting of personal protective
device
If the personal protective device on the
CHARGESTORM® Connected is triggered,
open the front panel with the key and reset the
device.
5 Testing
After installation, perform the following tests on
all the charging stations (if no other test
instructions are available).
To do this you need access to a chargeable
vehicle, or to a CHARGESTORM® Connected
test box that can simulate charging.
5.1
Testing of electric vehicle
connector
Connect the electric vehicle connector to the
vehicle and verify that charging has started.
The LED indicator turns blue during charging.
5.2
Earth fault testing
Press the test button on the residual current
device in the CHARGESTORM® Connected
and note whether the device trips. If there is an
earth fault, the 'X' will turn red.
CTEK E-Mobility
5.3
Connect electric vehicles to all the units and
check that the sub-unit is showing that the total
current does not exceed the rated current.
Fault reporting
Any faulty units should be sent to:
CTEK E-Mobility Center
Malmgatan 4
S-602 23 Norrkoping
SWEDEN
Tel.: +46 11 333 0002
Fax: +46 11 333 0003
Or to your local CHARGESTORM® Connected
distributor.
Include a fault description to help us locate the
fault.
www.ctekemobility.com