Installation

IMPORTANT
The EarthGuard must be installed in a clean, dry location away from direct sunlight and moisture.

Installation Standards

All installations must comply with national and local electrical standards and codes of practice. AERL
always recommends professional installation.
The EarthGuard EG-300 can be used to fulfil the earth fault/leakage detection requirements of AS/NZS
5033:2014 and 5139:2019 for unearthed PV and Battery installations.
Please refer to the Detection Requirements section below to determine the configuration that is required
for your application.

Detection Requirements

If the PV Array is not Galvanically Isolated from the battery bank (AERL and Victron regulators are not
isolated as they are Common Positive and Common Negative designs respectively), the battery bank's
potential Earth Fault Voltage is considered to be that of the connected PV Array and thus requires earth
fault/leakage detection on both the Battery and PV Array if the array exceeds 60Vdc.
That said, because the AERL and Victron regulators are not galvanically isolated, only a single
EarthGuard is required to cover both the array and battery bank due to the common (positive & negative)
electrical connections and the sensitivity of the EarthGuard device.
If the PCE is Galvanically Isolated, and the battery bank is below DVC-C, earth fault/leakage detection is
only required on the PV Array (provided it is above 60Vdc).

Mounting the Device

The EarthGuard should be fixed to a vertical surface using the mounting holes in the chassis flanges.
If the device is being used with an AERL CoolMax SRX Solar Charge Controller, the top plate can be
removed from the EarthGuard and the device can be mounted seamlessly against the base of the
CoolMax.
Seamless EarthGuard mounting requires that the CoolMax solar charge controller is installed using the
reverse cable entry ports, and the base cable glands have been removed from the controller prior to
installation of the EarthGuard device.