5.1
Push Button Installation (R920-E/F & R820-E/F Beacons)
If the E or F Series is wired for a push button but none is needed (such as
an advance RRFB), insulate the ends and secure the wires.
The push button can be connected in either polarity.
1. For round poles, cut holes to size and tap as required. Deburr the hole that the push button wiring will
pass through.
2. Feed the push button cable through the pole, creating a drip loop.
6.1
Battery Installation
Once the solar engine is secured and the beacons and other devices are in place, the batteries can be installed.
1. Open the solar engine and install the batteries, connecting each battery using the correct polarity. Secure
batteries with battery strap; note proper routing.
2. Batteries must be installed with the terminals facing outward (E Series, left image below) or upwards (F
Series, right image below).
3. The system will power up once the batteries are connected. If it is part of a radio-connected group, all
members of the group will now be able to communicate with each other.