7. END PLATE
9. FINAL ALIGN & U-LEG TRIM
Expansion Joint Material
per Structural Engineer
11. FLOOR CONCRETE PLACEMENT
Blank or Inlet End
Plate (as Specified)
Attach End Plate
to Channel with
Adhesive, Caulk
or Duct Tape
Verify Trench Alignment
and Elevation
Cut Excess Length
from U-Legs
Locate Grates to
have 1/8" [3 mm]
Gap Between Ends
Remove Foam After
Concrete Placement
8. PLACE ANCHOR SLAB
See Step 1 for Dimensions
Remove Suspension
Lumber as Required
10. ENCAPSULATION CONCRETE
PLACEMENT & CONSOLIDATION
Rotate Toggle to Clear Angle
Rails During Grate Placement
12. GRATE INSTALLATION
Use Vibrator to Consolidate
Concrete
Batter Boards
as Required
Place Evenly
Both Sides
Nut Nubs on
Bottom of Toggle
Tighten Screw Until
Toggle Bottoms on Grate