DanPumps S-WP3 Instrukcja instalacji - Strona 8

Przeglądaj online lub pobierz pdf Instrukcja instalacji dla Pompa wodna DanPumps S-WP3. DanPumps S-WP3 20 stron. Submesible wastewater pumps

Direct start
The motor guard is set to the current (measured in ampere) that is stated on the identification plate. When
the thermal surveillance is connected, the motor guard's setting is increased by 10%.
Star-delta start
The motor guard is set to the current (measured in ampere) that is stated on the identification plate multiplied
by 0.58. When the thermal overload switches are connected add 8% to the calculated value.
The grid must be secured with ordinary safety cutouts.
Thermal protection:
All pumps are equipped, with thermal overload switches built into the stator. These are marked F0 & F1. The
thermal protection conductors must be connected in series with the motor guard in the extern control board.
If this protection is not connected the guarantee will be void in case of damage.
See also technical specification.
Moisture sensor:
The conductor marked "D1" is connected to a moisture sensor, which is placed between the oil housing and
the motor housing. This sensor must be connected to a relay in the extern control board.
If moisture is registered in oil or stator housing, will the moisture relay cut off.
Your local DanPumps A/S dealer can supply you with the correct relay as an accessory.

8. Operation.

Before start, the pump must be fully assembled and ready for operation, and this manual read through.
Before the pump is started, the rotation direction must be checked.
At start the motors starting torque will cause the pump to jerk. The start reaction will be counter-clockwise,
seen from the top of the motor.
The starting torque can be very powerful even with small pumps. Never hold on to the
pump and do not start the pump when hanging in free air.
Place the pump solid so it cannot rotate or tip over before starting.
Never start the pump without impeller, the pump must be fully assembled and ready for operation.
At wrong start reaction two phases must be switched at the extern control box.
Never start up a pump with incompletely connected cables or non-operational overload switches and
leakage sensor.
Let a qualified electrician do this job.
9. Service & maintenance.
Before any inspection, service or repair of the pump, it must be physically disconnected from the electrical
power supply. Remove connectors or dismount the wires on the electric board.
(Any emergency stop can be released or be defective and start the pump by mistake)
All pumps require regular control and preventive maintenance to operate economically and reliably.
The pump should be checked every 6 months and during possible extreme operating conditions more often.
For complete overhaul of the pump contact an authorized DanPumps A/S workshop, or your local
DanPumps A/S dealer.
Clean the pump carefully before dismantling it. Follow local and national safety instructions.
Service Instructions for the S-WP pumps.
Type W - Wet Pit Installation
Install on a guide rail system, with a quick-release discharge connection bracket (DCB). The DCB is bolted to
the floor of the tank / well. The volute is equipped with an adapter to guide the pump via two 2" guide rails, to
secure connection on the DCB.