AddEnergie CoRe+VBV2 Manual de instalação - Página 12

Procurar online ou descarregar pdf Manual de instalação para Carregador de bateria AddEnergie CoRe+VBV2. AddEnergie CoRe+VBV2 14 páginas.

Preliminary Tests and Commissioning

2016 ADDÉNERGIE TECHNOLOGIES INC. ALL RIGHTS RESERVED. Information and Specifications Contained in this Document are Subject to Change, Amendments, and Additions at any Time, Without Notice
Instructions:
• Apply power to the charging station, the following should be
observed immediately after power is turned on:
1: The status light is on continuously, its color will be green
2: The display shows the greeting message
• Scan the access card provided with the charging head , these
results should be observed:
1: Once the reader detects the card, it will emit an audible bip
2: Immediately after the bip, the access card will be
authenticated by the charging station.
3: If the authentication of the card is successful, the automated
test of the protection circuit will be performed.
4: Once the test is successfully completed, the overhead status
light will start flashing (white).
5: If the connector is inserted into an Electrical Vehicle, it will
begin charging, if not, after 1 minute, the station will be in wait
mode.
• Once the preliminary test is successfully passed, the charging
station can then be used as a private charging station (using the
provided access card(s)), or to be connected to AddÉnergie's
management system by turning on the communication Gateway
provided by AddÉnergie.
12