8. When flow is established steady enough that
the inlet (upstream) block valve is fully open,
begin to slowly close the bypass valve and
continue until fully closed.
9. Develop system flow to a level near its ex pect ed
normal rate, and reset the reg u la tor setpoint
by turning the pi lot valve ad just ing screw
V. SHUTDOWN
A. General
1. On systems with a bypass valve, and where
system pressure is to be main tained as the
POSR-1 is shut down, slowly open the by pass
valve while closing the inlet (up stream) block
valve. Fully close the inlet (up stream) block
valve. (When on by pass, the sys tem pres sure
must be con stant ly ob served and man u al ly
reg u lat ed.) Close the outlet (down stream)
block valve. Close the nee dle valve on the
pilot valve's sensing line.
VI. MAINTENANCE
SYSTEM UNDER PRESSURE. Prior to performing any
maintenance, isolate the regulator from the sys tem and
relieve all pressure. Failure to do so could result in
personal injury.
A. General:
1. Maintenance procedures hereinafter are based
upon removal of the regulator unit from the
pipeline where installed.
2. Owner should refer to owner's procedures for
re mov al, handling, cleaning and dis pos al of
nonreusable parts, i.e. gaskets, etc. Cash co
recommends not reusing any gas kets, but
replacing with only new and fac to ry supplied
gaskets.
3. This regulator is supplied from the factory
using a gasket sealing aid, Federal Pro cess
Company, PLS 2, or equal. Such compatible
sealing aids may be utilized by the Owner, if
desired.
4
CAUTION
CW (viewed from above) to in crease outlet
pressure, or CCW to reduce outlet pres sure.
10. Reduce system flow to a minimum level and
observe setpoint. Outlet pressure will rise from
the set point of Step 9. There should be no
more than a 10% vari a tion in outlet pres sure
over the max i mum to min i mum flow range.
SECTION V
Do not walk away and leave a bypassed reg u la tor
unattended when on manual bypass!
2. If the regulator and system are to both be
shut down, slowly close the inlet (up stream)
block valve. Close the out let (down stream)
valve only if reg u la tor re mov al is required.
Close the needle valve on the pilot valve's
sensing line.
For POSR-1-20 close manual loading valve
and relieve loading pressure.
SECTION Vl
4. All indicated item numbers that are with
respect to the Pilot Valve will be in pa ren the sis
and underscored, i.e. (14), (PV). All item
numbers that are with respect to the Main
Valve will NOT be underscored, i.e. (1), (MV).
5. Refer to Figures 3 and 4 for item num ber
callouts.
6. Most pilot-operated valve operation problems
center around the pilot valve (PV). Cashco
always rec om mends full maintenance on any
POSR-1 pilot valve (PV) once a POSR-1 is
removed from the pipeline.
B. Separation:
1. Observe position of pilot valve (PV) with
respect to main valve (MV) before
dis as sem bling.
2. Place main valve body (1) into a vise, oriented
to allow rotation of pilot valve (PV) to geth er
with in ter con nect ing pipe nipple (19).
3. Remove loading tubing (21) at both end fit tings
(20) by rotating nut CCW (viewed from tube-
end).
CAUTION
IOM-POSR-1