cashco POSR-2 Manual de instalação, operação e manutenção
Procurar online ou descarregar pdf Manual de instalação, operação e manutenção para Controlador cashco POSR-2. cashco POSR-2 20 páginas. Pilot operated pressure reducing regulator
![cashco POSR-2 Manual de instalação, operação e manutenção](/uploads/products/server2/1653032/1653032.jpg)
ISO Registered Company
PILOT OPERATED PRESSURE RE DUC ING REGULATOR
. DESCRIPTION AND SCOPE
I
The POSR-2 is a pilot operated pressure reducing reg u la tor used to control downstream (P
1", 1-1/2", 2", 3" and 4" (DN25, 40, 50, 80, 100). The unit is suitable for steam service only. Refer to Technical
Bulletin POSR-2-TB for design conditions and selection recommendations. NOT RECOMMENDED FOR DEAD
END SERVICE.
II. INSTALLATION
A. General:
Do not dead end (no flow demand) downstream of POSR-2
if P
- Inlet Pressure is greater than max i mum allowable
1
outlet design pressure.
Spring Range
5-15 psig (0.34–1.03 Barg)
10–40 psig (0.69–2.8 Barg)
30–80 psig (2.1–5.5 Barg)
70–150 psig (4.8–10.3 Barg)
B. Piping the Valve:
1. An inlet block valve should always be in stalled.
2. If service application is continuous such that
shut down is not readily accomplished, it is
recommended that an inlet block valve, outlet
block valve, and a manual bypass valve be
installed.
3. Pipe unions are recommended for NPT
screwed in stal la tions to allow removal from
piping.
4. An outlet pressure gauge should be located
ap prox i mate ly ten pipe diameters down stream,
and within sight.
5. All installations should include a downstream
re lief device if the inlet pressure could exceed
the pressure rating of any downstream
equip ment or the maximum allowable outlet
pres sure rating of the unit.
INSTALLATION, OPERATION & MAINTENANCE MANUAL (IOM)
MODEL POSR-2
WARNING
Max. Allowable
Outlet Pressure
100 psig (6.9 Barg)
200 psig (13.8 Barg)
200 psig (13.8 Barg)
200 psig (13.8 Barg)
SECTION I
SECTION II
Recommended Piping Schematic for POSR-2
Installation of adequate overpressure pro tec tion is
recommended to pro tect the reg u la tor from overpressure
and all down stream equip ment from damage in the event
of regulator failure.
For welded installations, all internal trim parts, seals and
diaphragm(s) must be removed from reg u la tor body prior
to welding into pipeline. The heat of fusion welding will
dam age non-metallic parts if not re moved. NOTE: This does
not apply to units equipped with extended pipe nip ples.
6. Clean the piping of all foreign material in clud ing
chips, welding scale, oil, grease and dirt
before installing the regulator. Strainers are
recommended.
IOM-POSR-2
) pressure. Sizes are
2
FIGURE 1
CAUTION
CAUTION
02-20