Install RTD Probe:
7. Install RTD and connect wiring to connector block J9. (See Page 6
and Figure 5)
Install Battery(s):
8. Verify that the Memory Backup is Enabled. This is J1, terminals 1 &
2. (See Page 7 and Figure 5)
9. Mount and connect a fully charged battery to the battery connector
J6. (See Page 7 and Figure 5)
10. The display should go quickly through the startup routine then start
scrolling through the default display items. (If not, see Tip on Page
19) This typically insures that the components and wiring are good.
Refer to "Standard Displays" on page 15 for typical default displays.
Refer to "Visual Alarm & Status Codes" on page 16 for location,
symbols, and descriptions. You should see a LC code in the A7
annunciator (See Figure 10) since the charging source has not been
connected. This is the typical annunciator for the I/O Subsystem
application but could vary on different systems.
Install Solar Panel:
11. Assemble, mount, and connect solar panel or AC charger. NEVER
CONNECT CHARGER WITH THE MAIN BATTERY PACK
DISCONNECTED. (See pages 8 & 9) The LC code should go away
after the charging source is connected. Solar powered units will
naturally depend on available sunlight.
Setup:
12. Connect FS/2 or laptop running PCCU32 to the unit. To use an FS/2,
the µFLO must have been ordered from factory with FS/2 support.
PCCU32 must have software Version 4.3 or higher and the FS/2
must be 2018583-007 or higher.
13. Configure µFLO: Set date/time, ID, location, AGA setup, using Entry
Mode in PCCU32 or an FS/2.
14. In Calibration Mode, verify registers for Static pressure, Differential
pressure and Temperature. (PCCU32 Only)
15. In Calibration Mode, select RTD Installed, un-check Use Fixed TF,
and adjust RTD Bias if a temperature standard is used.
16. In Calibration Mode, perform as found calibration checks.
4