Cisco 8000 Series Preparar a instalação - Página 9

Procurar online ou descarregar pdf Preparar a instalação para Telefone IP Cisco 8000 Series. Cisco 8000 Series 10 páginas. Ip phones with multiplatform firmware
Também para Cisco 8000 Series: Manual de instalação (39 páginas)

Cisco 8000 Series Preparar a instalação
Prepare for Installation
Procedure
Step 1
Place the rack at the location where you plan to install the chassis.
Step 2
(Optional) Secure the rack to the floor.
To bolt the rack to the floor, a floor bolt kit (also called an anchor embedment kit) is required. For information
on bolting the rack to the floor, consult a company that specializes in floor mounting kits (such as Hilti; see
Hilti.com
bolts is required.
Note

Clearance Requirements

To ensure adequate airflow, we recommended that you maintain a minimum clearance distance always, as
mentioned in the following figure.
Following figure shows the clearances required for installation of Cisco 8800 Series Routers.
Figure 3: Clearances Required Around the Chassis
(1) Vertical rack post
(2) Vertical rack rail
(3) Chassis
for details). Make sure that floor mounting bolts are accessible, especially if annual retorquing of
Ensure that the rack in which the chassis is being installed is grounded to earth ground.
(8) Mounting depth of rack vertical rails
(9) Chassis depth
(10) Depth from the vertical rack rail to the front of
the chassis
Prepare for Installation
Clearance Requirements
9