Chapter 4
Carefully move the chassis into place over the bolt holes. See the
Step 4
section on page 3-5
Note
Step 5
Lock the dolly caster anti-rotation and brake systems.
Step 6
With a person on each side of the chassis, turn all four lifting cranks of the dolly counterclockwise slowly
to lower the chassis to the floor.
Note
Remove the dolly from the chassis.
Step 7
Warning
Insert all anchor bolts.
Step 8
Tighten all bolts and nuts.
Step 9

Unpacking Chassis Components

The remaining shipping boxes and pallets are now ready to be delivered from the receiving/shipping
dock or a site holding area to the final location of the chassis.

Steps

If possible, move the pallets to the same location as the unpacked and secured chassis. If not possible,
Step 1
move the individual boxes containing the various components to the chassis location.
Note
Step 2
Unpack all primary pallet parts from the packaging, and set the parts aside for installation.
Step 3
Unpack all secondary pallet parts from the packaging, and set the parts aside for installation.
Note
OL-29233-01
for details on moving the chassis with the dolly.
Where side clearance is not enough to use the dolly, you must first lower the chassis to the floor
and then slide it into place.
The dolly has four separate lifting cranks, each of which works independently when lifting or
lowering the chassis. It is best to turn the lifting cranks simultaneously when lifting the chassis
so as to not put undue stress on the chassis frame or dolly and reduce the risk of tipping too far.
Do not permanently locate the equipment on the dolly. Safely store the dolly after use.
Statement 357
All components are packaged separately. Cards are attached and installed on a wooden board
insert held in place by captive Phillips screws.
Do not unpack individual cards until you are ready to install the cards in the chassis.
Cisco Network Convergence System 6000 Series Routers Unpacking, Moving, and Securing Guide
Unpacking Chassis Components
"Moving the Unpacked Chassis"
4-3