ATTENTION
The following steps are for the rectangle
●
shower tray.
STEP 1
Ensure that the floor and the studs are at right angles.Provide a 5"×5" opening in the subfloor
●
for the drain. The 2" PVC waste pipe should extend above the surface of the sub-floor according
to the drain installation instructions and the height of the Shower Tray.
Mark unit position on floor and through drain opening.
●
Mark the locations of the studs on the flange of the base.
●
These marks are used to verify base location after drain is installed. (Fig 1)
●
The pipe height (A) shall be determined according to the products on hand.
●
C
5"
(12.7 cm)
A