Installation Recommendations
1. Use a separate trap for each unit, coil, surface,
chest, etc.
2. Include unions in inlet and outlet piping if trap will
be removed from installed location for cleaning
and maintenance.
3. For piping conditions in step 12, for siphon-drained
equipment and for tilting jacketed kettle, specify
traps with "steam lock release valves" (SLR).
4. Provide condensate-collecting pockets for
traps draining steam mains, headers, risers
and branches.
5. Ensure that return main is large enough to handle
the condensate from all traps discharging into it,
without causing excessive back pressure.
6. Always discharge high and low pressure traps into
separate return mains.
Figure 2. Recommended Piping Layouts
7. If possible, do not install trap with a long horizontal
run of piping between equipment outlet and trap
inlet. If such a hook-up is necessary, specify traps
with "steam lock release valves" (SLR).
8. Do not include a by-pass around trap unless
equipment drained must be kept in operation while
trap is being cleaned or serviced.
9. Do not jeopardize the advantage of a freeze-
proof trap by lifting the condensate or by the use
of horizontal piping from the trap outlet without
considerable pitch in the direction of flow or by
piping the trap in any way which will prevent fast
gravity drainage when steam is turned off.
Note
Do not insulate the trap or the piping and
fittings between equipment outlet and
trap inlet unless absolutely essential.
Do not use piping, nipples and fittings
smaller than trap connection size.