IMPORTANT
If unit is equipped with a crankcase heater and the
outdoor ambient air is 50ºF (10ºC) or below, it should
be energized 24 hours before unit start-up to prevent
compressor damage as a result of slugging.
6 - Set the thermostat for a cooling demand. Turn on
power to the indoor blower and close the outdoor
unit disconnect switch to start the unit.
7 - Recheck voltage while the unit is running. Power
must be within range shown on the nameplate.
8 - Check system for sufficient refrigerant using the
procedures outlined Section IV- subsection C-.
IV-CHARGING
CAUTION
ANY
NITROGEN
CYLINDER
SYSTEM MUST HAVE A 150 PSIG MAXIMUM SETTING
REGULATOR. NEVER INTRODUCE PRESSURES
GREATER THAN 150 PSIG TO ANY REFRIGERANT
SYSTEM.
A-Leak Testing
IMPORTANT
Leak detector must be capable of sensing HFC
refrigerant.
WARNING
Refrigerant can be harmful if it is inhaled. Refrigerant
must be used and recovered responsibly.
Failure to follow this warning may result in personal
injury or death.
CONNECTED
TO
Page 11
WARNING
Fire, Explosion and Personal Safety hazard.
Failure to follow this warning could result in
damage, personal injury or death.
Never use oxygen to pressurize or purge
refrigeration lines. Oxygen, when exposed
to a spark or open flame, can cause fire and/
or an explosion, that could result in property
damage, personal injury or death.
1 - Connect an HFC-410A manifold gauge set as
illustrated in figure 13.
2 - Open the valve on the HFC-410A cylinder (suction
only).
3 - Open the high pressure side of the manifold to allow
HFC-410A into the line set and indoor unit. Weigh in
a trace amount of HFC-410A. [A trace amount is a
maximum of two ounces (57 g) refrigerant or three
pounds (31 kPa) pressure].
4 - Close the valve on the HFC-410A cylinder and the
valve on the high pressure side of the manifold
gauge set.
5 - Disconnect the HFC-410A cylinder.
6 - Connect a cylinder of dry nitrogen with a pressure
regulating valve to the center port of the manifold
gauge set.
7 - Adjust dry nitrogen pressure to 150 psig (1034 kPa).
Open the valve on the high side of the manifold
gauge set in order to pressurize the line set and the
indoor unit.
8 - After a few minutes, open one of the service valve
ports and verify that the refrigerant added to the
system earlier is measurable with a leak detector.
NOTE - Amounts of refrigerant will vary with line lengths.
9 - Check all joints for leaks.
10 - Purge dry nitrogen and HFC-410A mixture.
11 - Correct any leaks and recheck.
12 - After leak testing, disconnect gauges from service
ports.