6. An east-west connectivity check is done by pinging between the servers in the FX2 chassis on all
applicable VLANs traversing FN410S-A2.
The FC630 server at 192.168.1.1 successfully pings the FC630 server at 192.168.1.3 via FN410S-A2 on
VLAN 6 without going through the ToR switch.
Note: If you want to verify east-west traffic bypasses the ToR switch by shutting port channel 128,
disable UFD on the FN410S first. Instructions for disabling and re-enabling UFD are in the appendix of
the
Dell PowerEdge FN IOM Easy Deployment Guide.
All connections have been verified and the upgrade is complete.