1. Commissioning Procedures

1.1. Checking Before Power-On

No.
Check Item
1
Mounting environment
Battery pack and
2
inverter mounting
3
WiFi mounting
4
Cable layout
5
Cable tie
6
Grounding
7
Switch and breakers status
8
Cable connections
Unused power
9
terminals

1.2. Powering on the Product

Check the voltage range and frequency range of the grid and the installation of
CT(s) or meter(s).
Switch on the battery breaker of the battery.
Switch on the battery breaker located on the energy storage inverter.
Switch on the external AC breaker between the grid and the energy storage
inverter.
Firstly, don't press the battery button, don't switch on the PV switch on the energy
storage inverter and don't switch on the AC breaker on the PV inverter if there is
any.
Commissioning Procedures
Acceptance Criteria
The mounting space is proper, and the
mounting environment is clean and tidy,
without foreign objects.
The battery pack and inverter are mounted
correctly, securely, and reliably.
The WiFi module is mounted correctly,
securely, and reliably.
Cables are routed properly as required by
the customer.
Cable ties are secured evenly and no burr
exists.
The ground cable is connected correctly,
securely, and reliably.
The PV switch and battery breakers and all
the breakers connecting to the product are
OFF.
The AC cables, PV cables (if there is any),
battery power cables, and communication
cables are connected correctly, securely,
and reliably.
Unused power ports and communication
ports are blocked by watertight caps.