Installation (continued)
30. Assemble the six provided trim pieces (P). The two top pieces
will be labeled "A" at the 45 degree overlap and the two
bottom pieces will be labeled "B". The remaining two pieces
are for the sides and are interchangeable.
31. Starting at the audience side bottom right corner, align the
first piece of bottom trim (P) with the bottom edge of the
screen. The end should be approximately 3" from the corner
of the wall opening. When aligned, snap the trim (P) onto the
T-track while moving along the length of the piece until firmly
in place. Align the second bottom piece of trim (P) at the 45
degree overlap and snap onto the T-track starting at the
overlap while moving along the length of the piece until
firmly in place (Figure 10).
NOTE: Custom screens may use three pieces.
4
3
2
Corner
Cover
Trim Pieces
A
A
5
6
B
B
1
45 Degree
Overlap
32. Starting at the audience side bottom left corner, align a side
piece of trim (P) with the side edge of the screen. The end
should be approximately 3" up from the corner of the wall
opening. When aligned, snap the trim (P) onto the T-track
while moving along the length of the piece until firmly in
place (Figure 10).
33. Repeat Step 31 for the top trim pieces (P) and Step 32 for the
audience right trim piece (P) (Figure 10).
34. Place corner covers (Q) over each corner to check fit and
alignment. Adjust trim if necessary. When satisfied with
desired placement of all four corner covers (Q), peel the red
release liners from the two pieces of adhesive and firmly
press each corner cover into place (Figure 10).
35. Carefully remove the protective paper on the projector side
of the screen surface to complete the installation.