Prepare the installation site.

Provide drainage, water supply and electrical power to within 6 feet (2 m) of
ice machine in accordance with local and national codes. Outdoor installation
of low side is not recommended and will void warranty.
2.1
2.1
Installation site requirements
1/4" per foot
(6,4 mm per 0,3 m)
Electrical
• 120/60/1-5 amps
Potable water supply
• 10–70 psi (69–483 kpa)
• 45–90 F (7–32 C)
• Follett recommends the use of an in-line water filtration system (item# 00130286)
• This equipment is to be installed with adequate backflow protection to comply with applicable
federal, state, and local codes
Drain
(3/4" Barb)
• Minimum 8" radius on silicone drain line. Drain line from the ice machine must have at least
1/4" per foot pitch (6,4 mm/0,3 m).
Refrigeration lines
• 5/8" ∅ (15,8 mm) diameter suction line (insulated)
• 3/8" ∅ (9,5 mm) liquid line
HARMONY • TOP-MOUNT
3/8" ∅ (9,5 mm)
5/8" ∅ (15,8 mm)
1'
(3/8" push-in internal connection, 3/8" OD tubing required)
remote condensing
silicone tubing
3/4" barb x 3/4" FPT
3/4" MPT x 1" slip
1" Stand pipe/Drain
NEMA
5-15

Site preparation

Minimum 8"
radius
2 ft. x 1" OD