AirTechnic ENERGY BOX - TO 350 Montaj ve Bakım Kılavuzu - Sayfa 4
Isıtma Sistemi AirTechnic ENERGY BOX - TO 350 için çevrimiçi göz atın veya pdf Montaj ve Bakım Kılavuzu indirin. AirTechnic ENERGY BOX - TO 350 20 sayfaları. Ceiling type heat recovery unit (aluminium plate)
CHECK LIST
In the event of unit failure and pre-commissioning checks to be made are determined as follows; after checking this information,
please contact our company in case failure continues.
Make sure that the unit receives power and electrical grounding is made!
Make sure that the electricity cables are drawn from in the correct cross section!
(Please check whether there is heating on cables or not.)
Please check whether the cables in unit control panel are shielded (shielded
magnetic field) or not; make sure shielding is grounded. If not, please change them!
Make sure that fresh air and exhaust air filters are clean and they do not block
the flow of air!
Make sure there is the connection of drainage on the unit, check any possible
clogging in drainage line and clean if necessary!
Please check whether the diameter of the air duct connection of the unit and the
diameter of the spigot are the same. If the duct connection is smaller, change it
with the correct one.
Make sure the electrical connections of the unit are made as suggested on the unit
and in this guide, check if there is incorrect connection.
Make sure during the installation of the unit there is enough space for the service
and if there is not enough space, re-install again.
In extremely cold climate applications, frost may occur on the exchanger, apply
electric heater in fresh air intake section of the unit to get the temperature to -8 °C
and above.
After installing the unit, make sure that it does not create an abnormal sound or
vibration, if there is, make sure that rubber pads are used.
+30.211.70.55.500
Controls
+30.210.22.23.283
√
4