User Manual
1.4 – Mounting and Installation
A typical installation will involve mounting the wall plate into a pre mounted 2-gang or larger wall box, standard drywall
bracket or mud ring. Before starting, make sure the wall box where the unD6IO is to be installed is pre-wired with a
suitable CAT5e or better cable back to a PoE-enabled network switch or mid-span injector. If a mid-span injector is being
used, the cable should be connected to the port that supplies both Ethernet and power (refer to the mid-span injectors
manual if unsure which port is which). The unD6IO packaging includes all of the necessary screws for mounting the
product and the included Decora wall plate.
*Note: All Attero Tech products are tested using UTP cabling and it is recommended that UTP cabling be used when
installing them. STP cabling can be used for installation though care must be taken not introduce grounding issues into
the system by doing so.
Attach the network cable from the switch/mid-span injector to the Dante I/F port of the Dante unD6IO. If the switch or
mid-span injector is already running and PoE is enabled, the unit should power up and the green ID LED on the front of
the device should turn on.
With the cable attached, carefully place the unD6IO into the wall box taking care to not trap the cabling. Once fully in
place, secure it with the screws provided. Once the unit is secured in the wall box, fit the Decora plate over the front of
the unit and secure it with the screws provided with it. It is recommended to not over-tighten the screws that attach the
included Decora wall plate to prevent cracking it.
Figure 5 - Dimensioned Drawing
Attero Tech LLC 2017
Page 8
614-00029 Rev 02_b