VII. CLEANING PROCEDURE for MODEL PA1:
A. Pre-Sanitation:
1. Owner should refer to owner's op er at ing
pro ce dures for system shutdown to include
re liev ing all system pres sure.
2. System internal pressure must be at/near 0
psig (0 Barg). This will ensure plug (17) is fully
open. NOTE: Do not change range spring
(8) setting by rotating knob (3).
3. Insert the lock-open pin (19) into hole in the
spring cham ber (2). See Figure 2.
B. Sanitation:
1. Flush, drain and sanitize system in ac cor dance
to owner's spec i fi ca tions.
NOTE: CIP is limited to 50 psig (3.45 Barg)
maximum cleaning solution pres sure at 300°F
(149°C).
SIP is recommended to 20 psig (1.38 Barg)
sat u rat ed steam pressure; can withstand 30
psig (2.07 Barg), but may reduce elastomer life
expectancy.
IOM-PA1-PL1
SECTION VII
Owner's cleaning solution must be com pat i ble with
regulator's trim materials.
C. Post-Sanitation:
1. Prior to system start-up, remove the lock-open
pin (19) from the spring chamber (2). Unit is
again operative at the setpoint established
prior to cleaning.
CAUTION
5