1. Introduction

Cm Pelet-set 90, pellet based heating system (nominal burner output 60 to 90 kW) designed for
installation in combined boilers or biomass firing boilers EKO-CK P, with thermal output from 70 to
110 kW. These technical instructions present commissioning, as well as fine tuning of the burner
operating parameters. Installation, commissioning and fine tuning of Cm Pelet-set 90 must be carried
out by the manufacturer authorized fitter/serviceman
Use and maintenance instructions for Cm Pelet-set 90 in daily work are also supplied with these
instructions.
2. Mode at delivery
1. pellet burner CPPL-90
2. lower boiler door CPDV 60/70 for burner CPPL-90 (for boiler EKO-CK P 70) and CPDV
90/110 (for boilers EKO-CK P 90 and 110) - factory mounted onto EKO-CK P boilers
3. boiler control unit CPREG - touch
4. pellet feeder CPPT-90
5. pellet tank CPSP-800

3. Technical data

Description:
1. pellet burner CPPL-90
2. tube for connecting of pellet feeding flexible tube
3. connectors for connecting of burner with control unit
4. Backfilling sensor / temperature sensor on inlet tube that
is installed tube for connecting of pellet feeding flexible
tube (backfilling sensor is detailed in the
Technical instructions for use and maintenance)
5. burner cover
6. plastic and silicone pressure switch tube
7. feeder with electric motor CPPT-90
8. pellet feeder flexible tube
9. pellet tank CPSP-800
10. cover of opening for filling the pellet tank
11. lower lid for tank cleaning
12. opening for pellet feeder
13. openings for tank cleaning
14. lower boiler door adapted for pellet burner CPDV 60/70 for burner CPPL-90 (for boiler EKO-CK P
70) and CPDV 90/110 (for boilers EKO-CK P 90 and 110)
15. connector for pressure switch silicone pipe on the lower boiler door CPDV
16. boiler control unit CPREG - touch
17. micro switch for lower boiler door
Technical instructions for the commissioning and adjustment
3