ANCHOR INSTALLATION: RETROFIT INSTRUCTIONS
The Revolution lift should be installed in a deck or footing with the following
specifications:
1. MI N I MU M F O O T I N G S I Z E : 4 ' - 0 " x 4 ' - 0 " x 1 2 " T H I C K .
2. MINIMUM CONCRETE STRENGTH: 3000 PSI
3. R E I N F O R C E ME N T : # 5 R E B A R @ 1 0 " O N C E N T E R ( O . C . )
T o e n s u r e a d e q u a c y o f a n e x i s t i n g p o o l d e c k a 4 ' – 0 " s q u a r e p o r t i o n o f t h e e x i s t i n g d e c k
may be saw-cut, removed and replaced with a footing as specified above. The new slab
reinforcing shall be drilled and epoxied into the existing slab as shown on the next page.
If your deck or footing does not meet these requirements please call Aqua Creek for
recommendations. The anchor should be bonded (grounded) per local electrical code.
For decks that meet these requirements follow these instructions to install your anchor.
TOOLS & MATERIALS REQUIRED:
CORE DRILL
3 – 1 / 2 " C O R E D R I L L B I T
MARKING PEN
EPOXY (ANCHOR ADHESIVE)*
1. Select an anchor location using the diagram below and the ADA guidelines on
page 4. Mark the center of the anchor location with a pen or marker.
2. Using a 3-1/2" d i a m e t e r c o r e -drill bit drill a 3-1/2" d i a m e t e r h o l e a t t h e a n c h o r
location. Make sure to keep the bit square to the deck. Drill straight down to a
depth of at least 9" .
3. Remove plug and clean out the hole with a wire brush, and then insert an air
nozzle to the bottom of the hole and blow out the hole using a pump or
compressed air. Proper hole cleaning is essential. If the hole is wet, dry it out as
much as possible. A heat-gun may be helpful in drying out the hole.
4. Mask the top of the anchor so that no epoxy gets inside the anchor.
5. P l a c e t h e a n c h o r i n t h e h o l e a n d ' d r y -f i t ' i t f i r s t t o m ake sure the anchor will be
flush and plumb with the deck when installed. Adjust the hole as needed.
6. I n s t a l l t h e e p o x y i n t o t h e d i s p e n s e r a n d f o l l o w m a n u f a c t u r e r s ' i n s t r u c t i o n s t o
ensure that the epoxy is properly mixed and applied. USE ONLY THE
RECOMMENDED EPOXY AND ALWAYS FOLLOW THE INSTRUCTIONS
SO THAT FULL STRENGTH IS ACHIEVED.
7. Inject epoxy adhesive starting at the bottom until the hole is 1/3 to 1/2 full.
8. Install the anchor into the epoxy and push down until it is flush with the deck
surface. Clean off excess epoxy. Adjust the anchor to make sure it is flush and
plumb with the deck surface.
9. Let the epoxy cure for at least 24 hours before installing the lift (or where
a p p l i c a b l e a c c o r d i n g t o t h e m a n u f a c t u r e r s ' i n s t r u c t i o n s ).
*Use HILTI HIT HY-150 adhesive anchor or SIMPSON ET22 StrongTie anchor
adhesive or equivalent.
NOTE: BOND (GROUND) THE ANCHOR PER LOCAL ELECTRICAL CODE.
WIRE BRUSH
AIR NOZZLE & PUMP/COMP.
HEAT GUN (OPTIONAL)
MASKING TAPE