Altrex MiTower Güvenlik ve Montaj Talimatları Kılavuzu - Sayfa 5

Güvenlik Ekipmanları Altrex MiTower için çevrimiçi göz atın veya pdf Güvenlik ve Montaj Talimatları Kılavuzu indirin. Altrex MiTower 20 sayfaları.

Altrex MiTower Güvenlik ve Montaj Talimatları Kılavuzu
4. Parts
See Annex T1 for an overview of the parts and their mass.

5. Mounting instructions

See Annex T2 for an overview of the mounting instructions.
6. Check before use
1.
Check that the scaffold is horizontal (check using a spirit level)
2.
Check that the scaffold is assembled in accordance with this manual and in conformity with the configuration and ballast
table.
3.
Check that the environmental factors, such as swinging doors ,awnings that operate automatically, aboveground electrical
cables, traffic and/or passers-by, etc., do not lead to dangerous situations.
4.
Check that the scaffold can be used safely and that it is suitable for the intended purpose.
7. Assembling the MiTOWER / MiTOWER+
Assemble the components on the basis of the steps that are shown in appendices T3 and T4. Make all connections as
indicated in appendix T2. See the table below for reference to the appendix with the configuration table and composition per
type of rolling tower.
MiTOWER / MiTOWER+
Assembly steps even working heights
Assembly steps odd working heights
Building even working heights
13'9"
- MiTOWER:
-
- MiTOWER+: 13'9"
-
Step 1 (T3:1)
1. Start with two frames (T1: A). Install the wheels (T1: B) in the
frames and apply the brake [T2: F1-F2].
2. Install a double guardrail brace (T1: C) with the upper claw on top
of the 4th rung [T2: F3].
3. Level out the base section using a spirit level. If necessary, adjust the
wheel legs by screwing the wheel leg nut up or down.
Step 2 (T3:2)
1. Place two frames (T1: A) on top of one another and secure
[T2: F4-F6]. Repeat this step. Place these linked frames on the
base section and secure [T2: F5-F6].
2. Install a double guardrail brace (T1: C) with the upper claw below
the 8th rung [T2: F3].
3. Place a platform (T1: D) on the 8th rung [T2: F7-F9].
4. Install the triangular stabilizers (T1: E); [T2: F11-F15]. Check if all
stabilizers make good contact with the ground. Adjust the stabilizers if
necessary.
5. Slide out the platform's hanging mechanisms [T2: F10] and hang 2x
a double guardrail brace here.
6. Climb through the hatch and sit on the platform with your legs
through the hatch.
7. Mount 2x a double guardrail brace (T1: C) with the upper claw on
top of the 4th rung of the frames [T2: F3].
Step 3 (T3:3 / T4:3)
1. Climb down and on the platform's hanging mechanisms hang: 2x a linked frame (T1:A), [T2:F4], a platform (T1:D) and a double
guardrail brace (T1:C).
2. Access the platform, install the linked frames and secure them (F2: F5-F6]
3. Install a double guardrail brace with the upper claws under the 4th rung of the frames that have just been installed [T2: F3]
4. Place a platform on the 4th rung of the frames you have just installed [T2: F7-F9]
Step 4 (T3:4 / T4:3)
1. Climb down and on the platform's hanging mechanisms hang: 2x a double guardrail brace (T1:C) and (only if the required working height
has been reached) a toe board set (T1:F).
2. Climb through the hatch and sit on the platform with your legs through the hatch.
3. Mount 2x a double guardrail brace (T1: C) with the upper claw on top of the 4th rung of the frames [T2: F3].
4. Only once the required working height has been reached: install the toe board set (T1:F).
5. For higher working heights, repeat steps 3 and 4.
Annex
MiTOWER / MiTOWER+
Configurations MiTOWER
T3
T4
Configurations MiTOWER+
20'4"
-
20'4" -
26'11"
Always respect the maximum platform height as mentioned in chapter 2 of this manual.
Building odd working heights
10'6" -
17'1"
- MiTOWER:
- MiTOWER+: 10'6" -
17'1"
Step 1 (T4:1)
1. Start with two frames (T1: A). Install the wheels (T1: B) in the
frames and apply the brake [T2: F1-F2].
2. Install a double guardrail brace (T1: C) with the upper claw below
the 4th rung [T2: F3].
3. Place a frame on both frames of the base section (T1: A) and
secure [T2: F4-F6]
4. Level out the base section using a spirit level. If necessary, adjust the
wheel legs by screwing the wheel leg nut up or down.
Step 2 (T4:2)
1. Place a platform (T1: D) on the 4th rung [T2: F7-F9].
2. Install 2x a double guardrail brace (T1: C) with the upper claw on
top of the 8th rung [T2: F3].
3. Install the triangular stabilizers (T1: E); [T2: F11-F15]. Check if all
stabilizers make good contact with the ground. Adjust the stabilizers if
necessary.
4. Slide out the platform's hanging mechanisms [T2: F10].
Annex
T5
T6
23'7"
-
3
www.altrex.com
5