Cutler-Hammer EATON Ampgard Mark V Talimatlar Kılavuzu - Sayfa 4
Kontrolör Cutler-Hammer EATON Ampgard Mark V için çevrimiçi göz atın veya pdf Talimatlar Kılavuzu indirin. Cutler-Hammer EATON Ampgard Mark V 12 sayfaları. Solid-state, brush-type, synchronous motor controllers
Page 4
Mark V Controller Functions (Cont.)
The SCR field power supply QA1, QB1, QC1, QA2, QB2,
and QC2 supplies voltage (125 or 250 VDC) and current to
the motor field. The power supply comes in three sizes,
50, 100, or 200 amperes DC.
The printed circuit board provides gating signals for the
starting and discharge circuit and protective functions as
well as the SCR power supply.
The field power transformer must have either a 120 or 240
volt three-phase AC secondary. A 120 volt AC secondary
is required for the 125 VDC system. A supply of 240 volts
AC is required for the 250 VDC system. It may be con-
nected wye or delta. Do not ground the system. The
transformer is sized KVA = .17 x rated amps DC @ 125
volts DC or KVA = .34 x rated amps DC @ 250 volts DC.
Current transformers are furnished in the motor starter
(controller) to supply current to protective relays and
various meters in direct proportion to the line current.
CONTROLLER OPERATION
Figure 4 shows the field power supply controller in con-
junction with the motor controller for a synchronous motor
starter. Note that the connection to the field supply
transformer is between the contactor (M) and the IQ
component so that the current transformers sense motor
stator current only.
The field power supply controller consists of three types of
circuits, one each dedicated to (1) field power, (2) control,
and (3) motor starting. The six thyristors (SCR's), QA1
through QC2, are the main components of the field power
circuit. The control circuit controls the starting circuit and
the output of the field power circuit.
A motor start sequence is initiated by closing the line
contactor (M). This results in the motor stator and the
solid-state field power supply being energized.
On start-up, three-phase voltage signals are supplied to
terminals KA2, KB2, and KC2. The open-fuse detection
circuit requires about 100 milliseconds to determine that
all voltages are present. It then causes RLY1 to close the
circuit between terminals ST1 and ST2 on TB1 (Figure 5).
The light emitting diode, LED1 is lit. If any fuse opens
and voltage is lost at terminals KA2, KB2, or KC2, RLY1
will drop out to open the control circuit.
RLY1 and RLY3 may pulse open and closed during certain
types of faults causing the interposing relay "MX" to drop
out, insuring that the "M" contactor has dropped out. SYTR
remains energized until "M" drops out.
The motor starter, being energized, causes the motor field
to generate an output voltage at the instantaneous slip
frequency of the motor. This voltage is controlled by the
independently operating thyristor-controlled starting circuit
D1-Q4.
The voltage across the field starting and discharge
resistor (S/D RES) is monitored during the starting
sequence to determine the instantaneous slip of the motor.
A motor slip condition of less than 75% (more than 25%
speed) must be reached within the preset time (rotary
switch SW2), ranging from 0 to 9 seconds, or a stalled
rotor condition will be indicated by the incomplete-se-
quence relay (RLY3) being energized.
As the motor continues to accelerate and the motor slip
frequency becomes less than the level established by the
setting of rotary switch SW1 (0-9%), the gate drives to the
field power supply thyristors activate and the soft turn-on
circuit begins to apply DC voltage to the motor field. If the
motor does not synchronize, Q4 is gated on. At the same
time gating to QA1 - QC2 is inhibited until Q4 stops
conducting.
Once again QA1-QC2 is gated on, applying voltage to the
motor field. This process is repeated until the motor
synchronizes or until a fixed time in the range of 2.5 to 3.5
seconds elapses.
Should the motor continue to slip poles after the 2.5 to 3.5
second period has elapsed, as indicated by the starting
circuit thyristor (Q4) continuing to conduct, the incom-
plete-sequence relay (RLY3) will be energized indicating a
failure to synchronize.
If the motor fails to reach the expected slip frequency
within 34 or 40 seconds from the beginning of the start
sequence, the timeout (TO) function will operate and the
incomplete-sequence relay (RLY3) will again be energized
if this option is chosen (by inserting jumper TO). See
OPTIONS on Page 6.
When motor synchronization is being established, the
output voltage is sensed and regulation of the field voltage
is accomplished by appropriate control of the gating
patterns to the field power supply thyristors QA1-QC2.
I.B. 48008
Effective 11/97