Alvarado VSGX Kurulum ve Bakım Talimatları Kılavuzu - Sayfa 8

Eskrim & Kapılar Alvarado VSGX için çevrimiçi göz atın veya pdf Kurulum ve Bakım Talimatları Kılavuzu indirin. Alvarado VSGX 13 sayfaları. Waist-high security gate

Installation Steps

1.
Determine the location where the gate will be installed, taking into consideration the minimum width opening required. Refer to
the "Space Requirements" section on page 8.
2.
Mark the locations (perpendicular to the gate centerline) for the hinge post and latch post centerlines.
3.
Center the hinge post at the intersection of the gate and hinge post centerline.
4.
Center the latch post at the intersection of the gate and latch post centerlines.
5.
With the gate arm in its neutral (home) position, ensure the entire unit (including hinge post, gate arm, and latch post) are
parallel to the gate centerline. Both posts must be plumb and level to each other and square to the gate. Verify proper alignment
of the locking mechanism.
6.
Mark the center locations of the four anchor holes for both the latch post and the hinge post. Move the posts to the side and drill
a 5/8"-diameter hole at the center of each marked location. Drill each hole 3" deep.
For terrazzo, ceramic tile, or brick veneer installations, add the thickness of the finished floor material to the
NOTE
anchor hole depth.
7.
Vacuum out the holes thoroughly. Debris in the holes will prevent the anchors from tightening properly.
8.
Insert an anchor with the thread-side down into each hole. The anchors must be flush with the top of the concrete pad.
For electrical gates, go to the "Electrical Activation & Wiring Instructions" section on page 9.
9.
Place the hinge post back over the anchor holes. Anchor the hinge post with 4 each 3/8" - 16 x 2 1/2" HHCS bolts and flat
washers. Do not tighten the bolts completely.
10. Place the latch post back over the anchor holes. Anchor the hinge post with 4 each 3/8" - 16 x 2 1/2" HHCS bolts and flat
washers. Do not tighten the bolts completely.
11. Confirm the gate arm is properly aligned with the latch post when the gate arm is in the closed position by ensuring that the
gate arm, hinge post, and latch post are installed plumb with the floor while being level and square to each other.
It is extremely important that the hinge post, gate arm, and latch post be level. Use a level to verify that the
WARNING
hinge post, gate arm, and latch post are level horizontally with the floor and vertically level with each other.
12. Adjust and shim the post as required to properly align the gate. It is important that the posts be plumb and level with the floor for
the gate arm to self-close and center properly. The gate arm and latch post must be at a 90° angle.
13. Tighten all of the anchoring bolts to 20 ft.-lbs.
14. Install the two halves of the split base cover around the hinge post base plate using the supplied 8 - 32 x 1/4" screws. Secure it
by tapping down with a rubber mallet over the hinge post base.
15. Install the two halves of the split base cover around the latch post base plate using the supplied 8 - 32 x 1/4" screws. Secure it
by tapping down with a rubber mallet over the latch post base.
16. Final installation check:
Verify all anchor bolts are tightened to 20 ft.-lbs.
Verify the gate arm and latch post are at a 90° angle.
Verify both posts are plumb and level to each other and square to the gate arm.