Function
The device is supplied with DC auxiliary voltage via terminals A1(+) / A2.
Switching on the auxiliary voltage (Power-On) is followed by an internal
self-test for 12 s (see „Device test functions"). The test process is visible
with the status LED. After this, measurement of the insulation resistance
in the measuring circuits begins and the status LED changes into green.

Measuring circuit

(Insulation measurement between terminals L(+) / L(-) and PE1/PE2)
The insulation monitor RN 5897/240 can be used both with ballast (VSG)
and without VSG. Max. mains voltage and connection diagrams have to
be observed!
If the insulation monitor is operated without coupling device the terminals
L(+) and L(-) have to be connected directly to the voltage system to be
monitored. and the terminals VSG1/L(+) and VSG2/L(-) each have to be
bridged (see also operation with coupling device).
A broken wire detection that can be disabled provides a fault signal if both
terminals L(+) and L(-) are not linked by the connected network.
The type of the voltage system or the connection method (AC, DC, 3NAC)
has to be correctly adjusted on the rotational switch "UN".
Also the terminals PE1 and PE2 have to be connected with 2 separate
wires to the protective earth. An interruption of a wire also causes a fault
signal (see section "Behavior on faulty connection"). The monitoring of
the PE connection cannot be de-activated.
To measure the insulation resistance an active measuring voltage with
changing polarity is connected between L(+) and L(-) and PE1/PE2.
At the end of a measuring cycle the actual insulation resistance is produced
and indicated. The relay for alarm K1 switch when dropping under the
adjusted response value. In addition the status LED lights up red on alarm.
Manual reset of fault message
With the 2-section rotational switch "UN", manual or auto reset of the alarm
can be selected. If manual reset is activated the insulation fault signal of
the measuring circuit is stored when dropping under the adjusted response
value also if the insulation resistance goes back to healthy state. Pressing
the „Reset" button on the front side for 2 s, the alarm signal is reset if the
actual insulation resistance is in healthy state.
Indicator relay for insulation fault and device failure
The function of the relays K1 (contacts 11-12-14 for alarm) and K2
(contacts 21-22-24) can be altered between energised on trip (relay n.o.)
or de-energized on trip (relay n.c.). When energised on trip the relays
energize when the value drops below the setting or at decive failure, when
de-energised on trip, the relays de-energize when the value drops below
the setting or at device failure.
Semiconductor output to indicate the insulation resistance
On terminals Y1(+)/Y2 a galvanically separated semiconductor output is
available as PWM (Pulse width modulated) signal that shows the actual
insulation resistance. It is an opto-coupler output with open collector.
This means that an external circuit is required (ext. supply voltage and
pull up/down resistor).
Disable the measuring function
Using the external control input X1/X2 the measuring function of the
RN 5897/240 can be disabled. This could be used when several isolated
voltage systems with individual insulation monitors need to be coupled.
The measuring voltage is set to -90V (negative measuring phase) and
the evaluation of the measurement is stopped. The status of the output
relays is frozen and not changed any more. If the measurement is disabled
the status LED flashes continuously orange. Please be aware, only the
evaluation of the measurement is stopped and the measuring pulse is
interrupted! A high resistive disconnection to PE does not take place
(see internal resistance).
Function
Broken wire detection
As described in section "Measuring circut", the measuring circuits L(+)/L(-)
and the protective conductors PE1/PE2 are constantly monitored for wire
breaks – not only at Power-On or a manual or occasional automatic test.
The response time of PE1/PE2 monitoring is only a few seconds. The
response time of monitoring of L(+)/L(-) can be up to approx. 2 min. Broken
wire detection between L(+) and L(-) is performed via coupled alternating
voltage. This alternating voltage is short-circuited if the terminals are
connected to the connected mains at low-resistance. The device detects
that the mains to be monitored is properly connected.
Since this broken wire detection is carried out with alternating voltage, large
capacitances should be avoided between L(+) and L(-), since the capacitive
reactance of these capacitances also short-circuits this alternating voltage.
The device would no longer detect a connection fault on L(+)/L(-).
Especially parallel lines should be prevented over larger distances.
If larger capacitances between L(+)/L(-) cannot be avoided or if the coupled
alternating voltage interferes with the system, the broken wire detection
can be de-activated on the 2-section rotational switch "Rel. /VSG". It can
be altered between continuously disabled (Broken Wire Detect OFF), or
continuously enabled (Broken Wire Detect ON) for 10 seconds every 2
minutes. If the broken wire detection on L(+)/L(-) is de-activated no AC voltage
is injected. The broken wire detection on PE1/PE2 cannot be de-activated.
Device test functions
Principally, 2 different test functions are implemented: The "self-test" and
the "expanded test":
The self-test of the device is performed automatically after Power-On and
every full operating hours. It can also be triggered manually at any time by
pressing the "Test" button at the device front for 2 s.
With the self-test, contrary to the expanded test, the status of the Indicator
relays is not affected; the sequence is as follows:
The self test is indicated by the status LED with flash code 1 in orange colour.
First the negative measuring pules is activated for about 5 s and the internal
measuring circuit is checked on failures. Then the positive measuring pulse
is activated for about 5 s and more internal tests are performed. If no failures
are detected, the normal measurement continuous. The extended test is
started, when during or at the end of above procedure (12 s) the button
"Test" is pressed again for 2 s.
The procedure is the same as above (2 measuring phases with 5 sec each)
but in addition the output relays K1 and K2 go into alarm state and the PWM
on the semiconductor output drops to the lowest value. The Status LED
shows flash code 2 in orange colour. The test phases will be continuously
repeated. The extended test can be finished after the first complete
sequence (approx. 10 sec) by pressing the "reset" button for 2 seconds.
The device starts the insulation monitoring again.
U
Self test (Test 1)
Insulation
measurement
measurement
Duration: approx. 12s
Positive
Measuring voltage
Negative
1)
Test signal
2)
Reset signal
Alarm
Relay state K1 and K2
No Alarm
1)
Test signal: Button Test > 2 s or X1/X2 > 1.5 s and < 10 s
2)
Reset signal: Button Reset > 2 s or X1/X2 < 1.5 s
3)
To initiate the extended test (Test 2) the test signal must be operated
within the self test (Test 1) again.
4)
The reset signal has here no function, as the first complete sequence
of extended test (Test 2) is not finished.
2
Self test (Test 1)
Continuous extended
Insulation
Duration: approx. 12s
test (Test 2)
Duration: approx. 10s
3)
4)
07.07.23 en / 755A
Insulation
measurement
t
M12462